Martin Kessler



17-Nov-95 Launch from Kourou at 01.20 UT

19-Nov-95 Perigee Raising Manoeuvre (from 500 km to 1000 km)

21-Nov-95 Start of ``Satellite Commissioning Phase''

24-Nov-95 Apogee Lowering Manoeuvre - operational orbit attained

27-Nov-95 Ejection of ``Cryo-cover''

28-Nov-95 First light with ISOCAM - Whirlpool galaxy M51

29-Nov-95 First light with ISOPHOT - Gamma Draconis

30-Nov-95 First light with LWS - S106 a Bipolar outflow region

01-Dec-95 First light with SWS - Gamma Draconis

08-Dec-95 End of ``Satellite Commissioning Phase''

09-Dec-95 Start of ``Performance Verification Phase''

03-Feb-96 End of ``Performance Verification Phase''

04-Feb-96 Start of ``Routine Operations''

14-Feb-96 Press conference at Vilspa to announce results of ``Performance Verification Phase''